February 2012: Beard Oxford secures £1.5 million of new work for Defence Estates, Oxford University and Rutherford Appleton Laboratories . Beard Guildford appointed contractor for £1.7 million new Parish Centre for St Joseph's Church, Redhill . Beard Swindon commences refurbishment of £1.0 million conversion of Ivy House into new boarding house for Marlborough College and is the preferred contractor for various projects to the value of £0.7 million for Defence Estates .


Company Profile Operating Areas Accreditations and Awards Terms and Conditions
Construction Design and Build Refurbishment Restoration Repair and Maintenance
Our Objectives Our Vision and Values Best Practice Supply Chain Partnering Innovation Environmental Management Health and Safety
Customer Care Arts and Culture Commerce and Industry Defence Education Elderly Care Emergency Services Healthcare Oxford Colleges Restoration Sports and Leisure Substations and Railways
Ashmolean Museum Chase Hospice Corpus Christi College Cox Green Leisure Centre Fox End Cottage Great Oaks Country House Highwood House King Edward's School Lindsay Court Apartments Lydiard Millicent School Queens College UWE Wakefield House Wellington College
Committed People Management and Structure Board of Directors Careers Current Vacancies

 

 

 







Case Study - The Sheepdrove Eco Conference Centre

A new eco-friendly conference centre, opened by The Prince of Wales and awarded the Sustainability Award in the Civic Trust Awards.

This complex and challenging building constructed in an area of outstanding natural beauty features a variety of meeting spaces on two floors, an organic kitchen, dining room, farm offices and an eco-friendly shop. The main structure echoes the cruck frame of a long barn; its nine-metre high Douglas fir arches are a spectacular feature of the main auditorium, as is the rammed earth wall running the length of the building.

Beard succeeded in matching the Sheepdrove Eco Conference Centre's approach to sustainability by creating a truly “green” building using recycled and local materials.  The specification of materials was informed by a study of the ‘embodied’ energy used in their manufacture, therefore no PVC was used in the construction, electrical wiring, pipe work and flat roof membranes. The cubicles and sinks in the visitors’ cloakrooms are made largely from recycled plastic and waterless urinals and aerating taps reduce water consumption.

Challenges & Solutions

Before crane-lifting the timber arches into position, the Beard team had to design and build a complex scaffold structure that would be strong enough to hold them while they were bolted together.

Beard overcame a number of technical challenges such as learning how to build a rammed earth wall and reclaiming chalk from the excavations to build the wall.  The chalk mixture for the 450mm-thick rammed earth wall had to be prepared manually because it clogged both conventional and paddle cement mixers. The mixture was developed in test batches and applied in 150mm-thick layers.

To meet the unusually long lead times for many of the sustainable materials specified, Beard had to programme works carefully, months  in advance.

“Our vision was to get people onto the farm to experience natural farming systems at work, all the way from field to plate. This spectacular building provides an inspiring meeting space, which helps us to realise that vision.”
Peter Kindersley , Sheepdrove Organic Farm



Customer
- Sheepdrove Organic Farm

Architect - Alec French Architects, Bristol

Contract value - £3 million

Contract duration - 17 months

Procurement - Two-stage Tender